The objective of this "BOOSTER-CIRCULATION PUMP INSTALLATION PLUMBING SERVICES " is to explain the details regarding the BOOSTER-CIRCULATION PUMP MEP, and installation work activities.
Purpose
This method statement is to establish the methodology by (Company Name) for installation of water pump set system, which was found elevation discrepancy between IFC Drawing and Enabling Drawing. And to describe the procedures and means for the installation works, which are the guideline to ensure the works are completed under relevant specifications and drawings.
Scope of Work
The Scope of Works is containing all the procedures for the installation of the water pump at the water plant room in (PROJECT NAME).
Reference Documents
Reference is made to the design and construction contract, Mechanical Specification, and the Employers Requirements. The required local and or international standards for the Booster Pump Installation will be adopted (where applicable) for the execution of booster pump installation the works.
Standards
- Latest Drainage/Submersible System Specification
- Latest Drainage System Approval Shop Drawing.
- Latest Approved Infrastructure & Coordinated Shop Drawing
- British Standard Specification
- British Standard Code of Practice
- The tender drawing on which the tender is based and the schedule therein
- The work drawing/construction is prepared by the contractor for the execution of work at the site.
- As-Built drawing is the true record of the actual work carried out at the site.
Organization Chart and Responsibility
The Construction Organization shall be set up accordingly to progress our construction efficiently and timely. Different stages of management will be assigned with corresponding responsibilities & accountabilities, which are shown below:
The Project Manager (PM) will have the overall responsibilities & accountabilities for the execution and management of the project. The Project Manager will provide the direction to achieve the completion of the project following the contract terms and conditions.
Senior Mechanical Engineer with responsibility for overall engineering design and execution of site works and to ensure all method and construction procedure is approved by the relevant parties before work commences.
Project Coordinator with responsibility for overall process implementation & works coordination.
The Site Manager in charge of the construction works will be responsible for coordination with all concerned parties to ensure construction will be completed on schedule and as required by QCS and the Project's special Specifications.
The Site Engineer will supervise, and maintain the construction on site and should report to the site manager any existing unfavorable events if any.
The QC Engineer shall implement construction quality control; they should inspect the worksite from time to time during the construction, based on Inspection &Test Plan
The Safety Officer to ensure all workers/staff work in a free hazard environment and ensure PPE applies at site project. Achieve International Environment, Health and Safety Standard is safety in priority.
Resources
Main construction equipment
No major plant and equipment are required for this activity, minor equipment including as listed below is used for construction:
- Mobile Crane / Tower Crane
- Skids / Roller
- Spanners / Hand Tools
- Lifting Accessories e.g., chain, sling
- PP-R Pipes & Fittings
- Drilling Tools
- Construction Methodology
- Activities (Work Scope)
- Procurement of Domestic Booster / Circulation Pump sets – (Brand: NAME HERE)
- Transport and unloading of piping to pump set to pump plant room
- Installation of pumps
- Testing and commissioning
Mobilization Plan
Transportation on Site
The booster/circulation pump sets shall be transported and delivered to the sites as per the delivery schedule. The unloading of equipment will be using the resident mobile crane or tower crane or manpower (should condition permit) at the designated platform in coordination with other trade and cranes will be operated by the authorized licensed operator under project safety rules and regulations.
Storage
If pump sets are to be stored for later installation, care must be taken to protect the pump sets by proper stacking in the site store to protect them from damages.
Inspection of Equipment in Stores
Material Inspection Request (MIR) should be released and all materials delivered should not be used unless it has been inspected by the consultant and verified for conformance to specification.
Programmed Reference
The work program for the installation of pipe works would be as per the latest MEP Master Work Program.
Installation of Pump set
System Description
- Each packaged Booster pump set system (2 pumps – 1 duty and 1 standby) comes complete with a pressure vessel provided.
- The Packaged Circulation Pump set system comes only as two individual pumps with identical specifications and related useful details.
- The pumps are factory assembled onto a common base plate together with a factory assembled control panel.
- Gate valves, check valves, pressure gauges, butterfly valves, etc. are factory assembled and connection at the site is only to the suction and discharge header.
- The complete system is factory tested before delivery to the site. The control for the booster pumps (start/stop) is done by pressure switches.
- There is also a low-level float switch to prevent the dry run. Booster Pumps are operated in a lead-lag manner to rotate between two pumps to balance the operation hours.
Preparation Work
- Before the start of installation, the following are required to be carried out.
- Make sure that the site/building is ready for installation of the pumping system and unloading platform, equipment access hatch is provided before the material delivery.
- Make sure that the shop drawings have been approved by the consultant and the drawings have been coordinated with other services.
- The delivered pump sets shall be as per specification and ensure that all materials delivered are undamaged and protected.
- Ensure all the materials have been inspected and approved at the site as per the relevant Material Inspection Request form.
- Check the RC pump plinth and ensure that the dimension and location of the pump plinth are according to requirements.
- Inspect and carefully check that the top surface of the booster pump plinth is level.
- Inspect & Check carefully that the work area is clean & tidy
Installation of Water Pump Set
- Locate the booster pump set system onto the booster pump plinth.
- Adjust the orientation of the pump set system so that the suction and discharge header outlets are correct and in line with the suction and discharge pipe connection.
- Highlight and mark the position of the screw hole at the mounting base on the pump plinth.
- Remove the booster pump set and drill holes on the booster pump plinth based on the markings.
- Insert the drop-in anchor into the hole.
- Insert an anti-vibration neoprene pad at the bottom of the pump set system base frame to isolate any vibration from being transferred to the building structure. (If required)
- Adjust the booster pump set system to make sure it is appropriately level.
- Connect the suction and discharge pipes to the pump set system suction and discharge header connections.
Measure and Plan for Safety and Health
Personnel engaged with this work shall follow a safety and health Plan; Safety & Health Manager will nominate one safety officer to check and monitor safety and health plan implementation.
Emergency Procedures
In case of an accident, the following shall be activated:
- The area MEP supervisors shall act as the Rescue Team Leader and attend to the accident scene as soon as possible.
- The area MEP supervisors shall inform the emergency controller (Project Manager) of the accident.
- In the absence of the Project Manager, the HSE Manager shall act as the Emergency Controller, by the name (Name Here).
- The emergency controller shall make proper arrangements for transportation to send the injured person to the clinic or hospital if required.
- A portable warning device/alarm shall be available and used by the health and safety officer.
- Conduct fire drill training regularly.
- Proper signage board for the exit from the building to a safe platform.
- All information and details regarding the accident including information, description, photos, time, location, sources, witness statements, police, and medical reports shall be prepared and submitted by the Project Manager to the concerned party (s).
Permit requirements
- Vehicle permits for Trucks
- Permit to work at nights
- Welding work permit.
Measure and Plan for Environment Protection
- All employees engaged with this work shall follow the Environment Management Plan.
- The environment Manager shall arrange for one person to check and monitor the site environment.
- Environmental impact assessment and measures
Quality Plan
- Contractual requirements
- The site operatives shall follow Engineering and trading Quality Assurance Plan.
- Further information can be found on Engineering and trading relevant documents.
Inspection & testing
Testing and inspections will be performed by Engineering and trading the procedure should be subjected to relevant requirements.
![]() |
| METHOD STATEMENT FOR BOOSTER-CIRCULATION PUMP INSTALLATION PLUMBING SERVICES |


0 Comments