METHOD STATEMENT FOR INSTALLATION, TESTING & COMMISSIONING OF DIESEL GENERATOR SET

1-Purpose


The purpose of this Method Statement (MST) is to highlight the details to be carried out for the installation of [Write Generator power in KV] Package Diesel Generator Set to ensure that it complies with Project requirements and specifications.


2-Scope of Work

This written document applies to all installations of emergency and Packaged Diesel Generator Sets at [Company Name] & [Project Name]. MEP technicians/manpower, equipment, or devices shall be organized to meet the schedule as per the approved construction program.


3-Definition

Abbreviation

QAQC - Quality Assurance Quality Control

MS -Method Statement

MEP -Mechanical, Electrical, Plumbing

RFIA - Request for Inspection & Approval

MIR - Materials Inspection Request

ITP   - Inspection and Test Plan

TBT   - Tool Box Talk


Approved” or “Approval

This means accredited in writing by way of the relevant Engineers' Assistant acting inside the scope of their delegated authority.


Shop Drawings

This means drawings are produced where the agreement designs drawings require expressing in a more basic form to facilitate construction.


Final Inspection

This “Final Inspection” means the inspection of the records of works at completion or after pre-determined elements to make sure that all previous inspections and tests have been satisfactorily conducted and properly documented.


Materials

The term “Materials” means all items covering the materials/substances or equipment delivered to the work site must be incorporated into the project.


Method Statements

This means a detailed technical document to be read along with the drawings, specifications, standards, and codes of practice, technical datasheets, schedules, work instructions, and any other technical document related to a particular work.

Reference Documents – Specifications, Drawings. Etc.


Project Quality Plan

Project General Specifications

Approved Project Electrical Drawings

Approved Material Submittal

Manufacturer’s Recommendations / Installation Instructions


Tools and Equipment

Equipment / Instrument

Mobile Crane

Insulation Test Meter, Earth Resistance Tester & 11KV Tester

Multimeter Tester

Mechanical Test Tools: Torque Wrench


Tools

Electrician Hand Tools

Crimping Tools

Drilling & Grinding Machines

Spanners

Half Round file

Screw Drivers

Open and Box Wrench

Torque Wrench

Pliers

Crowbar & Hammer

Electrician Hand Tools

Crimping Tools

Drilling & Grinding Machines

Spanners

Half-Round files

Screw Drivers

Open and Box Wrench

Torque Wrench

Pliers

Crowbar & Hammer

4-Manpower


Staff:

Construction Manager

Site Engineer

Supervisor

QC Engineer / Inspector

Quantity Surveyor

Safety Officer

Labor

Foreman

Trade workers

Helpers / Labours

Banks man

Crane Operator

Rigger

Drivers


5-Responsible Personnel on Site

The Project Manager (PM) shall be responsible/accountable for the overall construction activities.

The manufacturer representative will be responsible for the overall supervision of Installation and Testing.

The Material/Asset controller shall be responsible/accountable for receiving materials in the on-site warehouse.

The safety Officer shall make certain that suitable/necessary measures are in the region at the painting area to avoid any unexpected activities.

QAQC Inspector will be chargeable for wearing out inspections for the substances brought on-web page. He shall document such inspections.

QAQC Engineer / Inspector shall display the installation activities progressively and shall file all deviations from the specification in the form of snags or similarly as non-conformance notifications.


6-Material Inspection / Storage

The Diesel Generator is enclosed kind, Cummins, Model- [00000], 00KV, 3phase, four Wire, 50Hz at 1500 pm.

The trailer with the Diesel Generator ought to input through the north/west/east/south and so forth. Avenue of the mission.

Road closure allows are to be obtained from the municipality earlier than the advent of the Generator presuming the timing of arrival.

Use the cell crane to off-load Generators. Make positive that the potential of the cell crane can convey the burden of the Generator.

The cellular crane and the trailer ought to be positioned in positive locations which makes smooth get entry to the Platform.

Use a cellular crane to offload the generator.

Ensure that the generator is properly protected and covered by a tarpaulin.

Before acceptance, an inspection regarding the physical condition shall be conducted to ensure that the materials are following the approved material submittal.


7-Construction Sequence and Methodology

Preparation before Installation

Make sure that the Drawings for Installation are approved & coordinated with other services.

Ensure that the material is free from damage before shifting to the areas of work. 